PDF File

Latest AACE International AACE-PSP Practice Questions BY Blankenship

Question 1

When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?

  • A. Projected crew size
  • B. Estimated labor hours
  • C. Hours in a standard work day
  • D. Estimated cost Estimating Activity Durations: The critical factors are crew size, labor hours, and the standard workday. Cost estimation is not directly required to calculate durations. Evaluation of Options: Option A: Incorrect. Crew size is needed for productivity estimation. Option B: Incorrect. Labor hours are directly tied to durations. Option C: Incorrect. Workday hours define the available time. Option D: Correct. Cost is not directly linked to duration