Question 1
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
A.Projected crew size
B.Estimated labor hours
C.Hours in a standard work day
D.Estimated cost
Estimating Activity Durations:
The critical factors are crew size, labor hours, and the standard workday.
Cost estimation is not directly required to calculate durations.
Evaluation of Options:
Option A: Incorrect. Crew size is needed for productivity estimation.
Option B: Incorrect. Labor hours are directly tied to durations.
Option C: Incorrect. Workday hours define the available time.
Option D: Correct. Cost is not directly linked to duration