Question 1

You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.

Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?

i. 95% of the tests prepared are executed successfully

ii. All test cases have been run

iii. 80% decision coverage for all tests run

iv. At least 30 defects have been found

v. At least two weeks of test execution

vi. No more open defects

  • A. iii for component testing, v for system testing
  • B. ii for component testing, iv for system testing
  • C. iii for component testing, i for system testing
  • D. v for component testing, vi for system testing
Question 2

During which test planning task are the test design techniques to be applied during the project, identified and selected?

  • A. Understand the context and organise test planning
  • B. Identify risk treatment approaches
  • C. Define test approach, and estimate and allocate resources
  • D. Establish test plan