PDF File

Latest PMI-SP Practice Questions BY Fuller

Question 1

John is the project manager for his organization. He has created a status dashboard for his stakeholders. What is a status dashboard?

  • A. It is a report that details the current status of risks and issues.
  • B. It is a software application that allows stakeholders to view the project manager's performance.
  • C. It is a web-based tool to inspect the project deliverables for performance.
  • D. It is a report that reflects the overall performance of scope, schedule, quality, cost, or other project performance metrics.
Question 2

You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

  • A. Project Human Resources Management Plan
  • B. Project Staffing Management Plan
  • C. Project Communications Management Plan
  • D. Project Schedule Management Plan