Question 1

What statement best describes the product backlog?

  • A. It is an emergent, ordered list of what is needed to improve the product
  • B. It is the diary of the product owner
  • C. It is mainly meant as inspiration for the sprint planning
  • D. It is a list of all the requirements that will have to be added to the product
Question 2

While developing new functionality, you find a bug that has already been delivered to the customer. What do you do?

  • A. Fix the bug
  • B. Revise the tests to hide the bug from the tests reports
  • C. Talk to the product owner
  • D. Stub out the code that causes the bug