PDF File

Latest IIBA CPOA Practice Questions BY Fox

Question 1

While the delivery team is busy building product features in ongoing iterations, the majority of a product ownership analysis (POA) practitioner's time will be spent in:

  • A. refining the product backlog for the upcoming iteration.
  • B. validating product features from the previous iteration.
  • C. clarifying delivery team queries.
  • D. monitoring progress of the delivery team.
Question 2

Details needed in the acceptance criteria of the product backlog item (PBI) should be:

  • A. achievable and testable.
  • B. very short and condensed.
  • C. functional and non-functional requirements.
  • D. about business benefits.